Newfoundland and Labrador Premier Tony Wakeham confirms preliminary hydro engineering work for Gull Island could commence in spring 2027 under the finalized tri-party energy accord.

ST. JOHN’S, NL — Premier Tony Wakeham addressed energy sector stakeholders and the House of Assembly Thursday night, detailing the operational timeline for the historic $70 billion Churchill Falls hydro renewal agreement reached between Newfoundland and Labrador, Quebec, and the federal government.
Premier Wakeham confirmed that provincial crown corporation Hydro will begin preliminary road access and environmental baseline engineering for the 2,250-megawatt Gull Island hydro development in spring 2027, provided definitive commercial contracts are executed by December 31, 2026. The tri-party framework guarantees that Newfoundland and Labrador will receive market-rate equity revenues for Churchill Falls power exports while securing joint financing from the Canada Infrastructure Bank (CIB) for clean transmission lines across Labrador and Quebec.
Wakeham affirmed that the agreement permanently rights historical economic imbalances, creating thousands of high-wage trade jobs in Labrador.
Opposition Liberal and NDP leaders called for an extended legislative debate, demanding that all financial risk-sharing terms and First Nations impact-benefit agreements be tabled in the House of Assembly for open committee scrutiny prior to final ratification.
Indigenous leadership in Labrador, including the Innu Nation, affirmed that free, prior, and informed consent (FPIC) and equity ownership are mandatory prerequisites for project construction.
Legal and financial negotiating teams from St. John’s, Quebec City, and Ottawa will convene weekly drafting sessions through November 2026.

Hydro-Québec announces a $340 million transmission line and substation refurbishment in the Saguenay–Lac-Saint-Jean region to power expanding aluminum smelters and data parks.

Alberta Utilities Minister and county commissioners conclude community town hall sessions on proposed multi-gigawatt artificial intelligence data center campuses in Sturgeon County.

The DOE releases final solicitation criteria for $450 million in cost-shared funding to license and deploy Gen III+ Small Modular Nuclear Reactors across industrial sites.