Bureau of Land Management issues final Record of Decision approving NV Energy's 525-kilovolt Greenlink West transmission corridor, unlocking 4,000 MW of solar and geothermal power from Las Vegas to Reno.

CARSON CITY, NV — The United States Department of the Interior (DOI) and the Bureau of Land Management (BLM) published the final Record of Decision approving the construction of the Greenlink West Transmission Project, a 470-mile 525-kilovolt high-voltage direct current (HVDC) transmission corridor traversing public lands from Las Vegas to Yerington and Reno.
The $2.5 billion transmission infrastructure megaproject connects massive utility-scale solar, battery storage, and geothermal generation projects across Esmeralda, Mineral, and Lyon counties directly to Nevada’s urban load centers, providing enough clean electricity to power 1.2 million homes. The project will create 3,800 union construction jobs and generate $690 million in direct economic output while strengthening Western regional electric grid reliability.
Interior Secretary Deb Haaland affirmed that approving major transmission corridors on public lands is vital to deliver clean, affordable energy to western communities and combat climate change.
IBEW Local 396 and Local 401 praised the project labor agreement, securing apprenticeship ratios and prevailing wages for electrical lineworkers.
Geothermal energy producers in Central Nevada noted that Greenlink West provides previously unavailable transmission interconnection capacity.
Transmission tower foundation construction will break ground in Clark and Nye counties in November 2026, with commercial operation slated for late 2028.
U.S. Department of Energy invokes Section 202(c) of the Federal Power Act, ordering PJM to maintain Units 3 and 4 at the Eddystone Generating Station through November 2026.

U.S. Department of Energy orders MISO to maintain the J.H. Campbell coal-fired plant in West Olive, Michigan, through November 2026 to protect Midwest regional transmission stability.

U.S. Department of Energy authorizes PJM to run Unit 4 of the Herbert A. Wagner Generating Station in Anne Arundel County, Maryland, through November 2026 to manage Baltimore grid demand.